High Street Drainage works to commence on the 27th September 2021

Following several chases the Parish Council have now been advised from Milton Keynes Council’s Environment & Property department that they intend to carry out the pipe work required in the High Street by the old chestnut tree.

They advise that the “work will be commencing on the 27th Sept 2021 by the chestnut tree to replace the surface water carrier pipe and to work on gullies in this location.

The work will be carried out under 3 way traffic lights and access will be maintained to the pub and residents properties while this operation is carried out.

Attached are TM plans as this work will be carried out in three phase to reduce disruption and accessibility to village.

1487- 3W TL, HIGH STREET, HAVERSHAM-PHASE 1 REV 1

1487- 3W TL, HIGH STREET, HAVERSHAM-PHASE 2 REV 1

1487- 3W TL, HIGH STREET, HAVERSHAM-PHASE 3 REV 1

A letter drop will also be carried out shortly to the residents of the village to inform them of upcoming works.”

 